Belmont Forum is undergoing a $65M redevelopment which includes the construction of a new Coles supermarket and new alfresco dining precinct.

Details

Perkins Builders engaged Fortec Australia on Stage 3A of this project to provide post tensioning services to the new car park slab.

The scope included:

  • Fix recess forms and anchorages.
  • Prestressing anchorages.
  • Place and fix ducting.
  • Install tendons.
  • Stress tendons.
  • Grout tendons.
  • Remove existing bearings.
  • Removal of staples.

Highlights

  • All works were self-performed by Fortec with only asphalt and seal being performed by sub contract.
  • The project was completed ahead of the client schedule.

Capabilities

  • Post Tensioning