Timber Bridge Replacements

Project Overview

Fortec recently obtained the B3 bridge prequalification reciprocal approvals in NSW which gave us the opportunity to tender and secure our first bridge replacement project in NSW.

A number of different schemes were assessed during the tender phase, with Fortec deciding on the InQuik system for the works due to the remoteness of the site.

The modular nature of the InQuik system will allow better control over both quality and program to ensure the project is delivered on budget and on time.

Site works commenced in early January 2023 with current programming having the five bridges complete towards the end of the year.

Fast Facts

  • ClientDungog Shire Council
  • LocationDungog, NSW
  • Year of completion2023

Scope of works

Fortec’s scope of works included:

  • Demolition of existing bridge structures
  • Design and construction of new bridge structures
  • Bored pile foundations, abutments, wingwalls and bridge deck
  • Utilisation of the InQuik Modular Bridge system for the abutment and bridge deck